Wilson Sporting Goods {www.wilson.com}
planned to move into a larger facility. To
assist with the move, Maron Structure Technologies prepared a plan for
powering down the equipment, moving it to the new location, and powering
the equipment back up in a coordinated sequence.
....
Maron Structure Technologies also remained
onsite to assist with the relocation effort and troubleshoot a few technical
issues. For example, the data center footprint was revised at the last
second to accommodate a few new racks for growth and Maron engineers had
to coordinate with the carrier after they missed an important deadline.
In the end, Maron Structure Technologies worked close to 75 hours in overtime
to ensure that doors opened without issue.
....
"They knew exactly what they were
doing and what needed to be done. They were very organized and the end
result was what we wanted," Barb Brunke, Technical Analyst II
.......................
|
 |
|